North High School and Middle School

Project:

North High School and Middle School
Evansville, Indiana

Owner:

Evansville Vanderburgh School Corporation

Contract Amount:

$12,000,000

Description:

BBI provided the site and utility work including clearing, earthwork, soil stabilization, storm sewer, sanitary sewer, water lines, stone base, and seeding. In addition, we are responsible for the paving, sidewalks, construction of tennis courts, soccer field, football field with synthetic turf installation, baseball and softball fields. The project had 300,000 cubic yards of excavation for the site of the new middle and high school buildings that, combined, total 500,000 sq ft and provide educational facilities for 20,000 students.