Scenic Lake Dam Rehabilitation

Project:

Scenic Lake Dam Rehabilitation
Henderson, Kentucky

Owner:

Kentucky Division of Engineering and Contract Administration

Contract Amount:

$1,500,000

Description:

BBI acted as the general contractor on this project and completed more than 90% of the work with our own forces. The project involved earthwork to widen the dam crest, construction of the downstream embankment blanket drain and toe drain systems, flattening of the dam downstream embankment, existing spillway modifications to new low level outlet, construction of new low level outlet gates and construction of a new baffle chute spillway.